The Ixonia LNG facility will be located in Jefferson County, Wisconsin in the town of Ixonia. The plant will be located approximately 5.7 miles southeast of the city of Watertown, Wisconsin and approximately 3.3 miles northwest of the city of Oconomowoc, Wisconsin.
The project includes a new LNG peaking facility, associated on-site pipelines and supporting equipment. The facility will be capable of liquefying, storing and vaporizing natural gas for peaking service.
Key project dates
Activity |
Time frame |
Construction start |
January 2022 |
Impoundment construction start |
March 2022 |
Tank foundation poured |
May 2022 |
Tank construction complete and commissioning begins |
Fall 2023 |
Project update
Construction of the Ixonia LNG plant continues to proceed on schedule.
Tank impoundment complete. Tank construction underway and plant foundations installed.
Previous updates
Approximately 800 yards of concrete has been brought in by truck from plants in Watertown and Whitewater. The trucks unload into the two red pumper trucks. Aerial booms connected to the trucks to bring the concrete to the foundation. Workers use vibrating equipment to move the concrete in between the foundation rebar.
Core project (on-site) work hours
Monday to Friday
7 a.m. to 5 p.m.
Saturday* 7 a.m. to 5 p.m.
Sunday* 10 a.m. to 5 p.m.
*Only as necessary
Typical delivery hours
Monday to Friday
8 a.m. to 2:30 p.m.