Ixonia project

The Ixonia LNG facility will be located in Jefferson County, Wisconsin in the town of Ixonia. The plant will be located approximately 5.7 miles southeast of the city of Watertown, Wisconsin and approximately 3.3 miles northwest of the city of Oconomowoc, Wisconsin.

Ixonia LNG facility

The project includes a new LNG peaking facility, associated on-site pipelines and supporting equipment. The facility will be capable of liquefying, storing and vaporizing natural gas for peaking service.

Key project dates

Activity Time frame
Construction start January 2022
Impoundment construction start March 2022
Tank foundation poured May 2022
Tank construction complete and commissioning begins Fall 2023

July 2022 — project update

Construction of the Ixonia LNG plant continues to proceed on schedule.

plant entrance paved

The plant entrance has been paved.

newly paved plant entrance

Newly paved plant entrance.

Ixonia LNG tank construction

Tank construction continues.

Previous updates

Crews are pouring concrete for the LNG tank foundation. Approximately 800 yards of concrete has been brought in by truck from plants in Watertown and Whitewater. The trucks unload into the two red pumper trucks. Aerial booms connected to the trucks bring the concrete to the foundation. Workers use vibrating equipment to move the concrete in between the foundation rebar. Once this work is done, crews will begin putting up the carbon steel outer tank.

Core project (on-site) work hours

Monday to Friday
7 a.m. to 5 p.m.
Saturday* 7 a.m. to 5 p.m.
Sunday* 10 a.m. to 5 p.m.
*Only as necessary

Typical delivery hours

Monday to Friday
8 a.m. to 2:30 p.m.