Ixonia project

The Ixonia LNG facility will be located in Jefferson County, Wisconsin in the town of Ixonia. The plant will be located approximately 5.7 miles southeast of the city of Watertown, Wisconsin and approximately 3.3 miles northwest of the city of Oconomowoc, Wisconsin.

Ixonia LNG facility

The project includes a new LNG peaking facility, associated on-site pipelines and supporting equipment. The facility will be capable of liquefying, storing and vaporizing natural gas for peaking service.

Key project dates

Activity Time frame
Construction start January 2022
Impoundment construction start March 2022
Tank foundation poured May 2022
Tank construction complete and commissioning begins Fall 2023

Project update

Construction of the Ixonia LNG plant continues to proceed on schedule.

Tank construction

Tank impoundment complete. Tank construction underway and plant foundations installed.

Previous updates

Approximately 800 yards of concrete has been brought in by truck from plants in Watertown and Whitewater. The trucks unload into the two red pumper trucks. Aerial booms connected to the trucks to bring the concrete to the foundation. Workers use vibrating equipment to move the concrete in between the foundation rebar.

Core project (on-site) work hours

Monday to Friday
7 a.m. to 5 p.m.
Saturday* 7 a.m. to 5 p.m.
Sunday* 10 a.m. to 5 p.m.
*Only as necessary

Typical delivery hours

Monday to Friday
8 a.m. to 2:30 p.m.