Ready for service requirements - electric
Send in your Electric Ready for Service Card (PDF 56k) after all requirements are met. Upon receipt, we will schedule an installation date.
- Locate, mark or expose any privately owned underground facilities or buried obstructions – such as a well or underground yard lighting – with stakes, spray paint or flags.
We Energies and/or its agents will not be held responsible for damage that occurs to customer-owned underground facilities that are not properly located and marked before electric service installation.
- Clear a 10-foot-wide path along the service route from the property line to the meter location. Make sure dirt piles, construction materials or other things are not in the way.
- Prepare the ground around your building and along the service route to within 4 inches of final grade.
- Send your:
Electric inspection certification from the municipality
Signed sketch (if applicable)
Payment (if applicable)
Note: Returning your Electric Ready for Service Card before completing all requirements may delay installation.