Ready for service requirements - electric

Send in your Electric Ready for Service Card (PDF 56k) after all requirements are met. Upon receipt, we will schedule an installation date.

  1. Locate, mark or expose any privately owned underground facilities or buried obstructions – such as a well or underground yard lighting – with stakes, spray paint or flags. We Energies and/or its agents will not be held responsible for damage that occurs to customer-owned underground facilities that are not properly located and marked before electric service installation.
  2. Clear a 10-foot-wide path along the service route from the property line to the meter location. Make sure dirt piles, construction materials or other things are not in the way.
  3. Prepare the ground around your building and along the service route to within 4 inches of final grade.
  4. Send your:
    Electric inspection certification from the municipality
    Signed sketch (if applicable)
    Payment (if applicable)

Note: Returning your Electric Ready for Service Card before completing all requirements may delay installation.