Primary Time-of-Use (CP1)


Overview

This rate plan is available to customers with service at approximately 3,810 volts or higher and to customers who own their own transformation equipment.

How it works

On-peak option hours are 8 a.m. to 8 p.m. or 10 a.m. to 10 p.m. The monthly minimum charge is the facilities charge plus either the charge for 300 kilowatts (kW) of billed demand or the minimum demand charge stated in a customer contract, whichever is greater, plus the customer maximum demand charge.

Tariff

Primary Time-of-Use Cp1 (65 to 71) PDF

Transmission level service

American Transmission Company (ATC) owns and operates the transmission system. For Cp1 service at voltages greater or equal to 69 kilovolts, We Energies and ATC work together to develop solutions for new interconnection substations.

Transmission level service through ATC